Trans Mountain sends signal to restart pipeline

The Canadian Press   

General Energy

Contractors given 30 days to get ready for construction despite new court challenges.

SHERWOOD PARK, Alta. – Trans Mountain Corp. has advised construction contractors to get ready for the restart of its pipeline expansion project to the west coast. The company says its directive gives contractors 30 days to ready equipment, start hiring workers, secure goods and services and develop detailed plans.

The company says work is to begin soon in communities along the right of way between Edmonton and Edson, Alta., and in the greater Edmonton area. Work is also to resume at the terminal in Burnaby, B.C., which is the end point for the pipeline that is to carry oil from Alberta to the coast for shipment to overseas markets.

Trans Mountain says specific start dates in the remaining construction areas are subject to final regulatory approvals and permits.

The federal government gave a second go-ahead to the expansion project in June after the courts overturned the original approval.

Advertisement

The Liberal government spent $4.5 billion to buy the pipeline from Kinder Morgan Canada in 2018 in a bid to get the existing pipeline expanded despite significant political opposition in British Columbia.

That plan was put on hold last August when the Federal Court of Appeal said the government had not done a good enough job consulting with Indigenous communities or studying the impact on marine life.

Six British Columbia First Nations and at least two environment groups have filed new court challenges.

“We are confident that we have a path forward by which the expansion project construction can commence,” Ian Anderson, President and CEO of Trans Mountain Corp., said in a release Wednesday.
www.transmountain.com